Construction of cogeneration unit in ZEC „Wesoła”

The subject of investment was the construction of cogeneration unit  in the operating power plant by the hard coal mine "Mysłowice - Wesoła", based on the gas engine with power 3MW. Control Process was responsible for engineering, delivery, assembling  and installation commissioning, that is going to use at least 5,5 mln m3 of methane annually.

Information

Project name Construction of cogeneration unit in ZEC „Wesoła”
Client Zakład Energetyki Cieplnej S.A.
Duration 2013 - 2014
Technical data Power: 3 MWe