Reconstruction of the gas compressor station in Jarosław
Within the project Control Process company acting as the General Contractor realized works including implementation of technology of gas boiler house, electric installation, water and sewer installation and vantilation. The scope of works included also ICA installation and the utilities monitoring system. Realization included also a complete technical and subcontracting documentation.
Information
Project name | Reconstruction of the gas compressor station in Jarosław |
---|---|
Client | GAZ-SYSTEM |
Duration | 2008 |
Technical data | Power: 3800 kW |