Development of natural gas deposit, Kupno
The project included comprehensive realization of construction-assembly works consisting in construction of complete natural gas mine within the Kupno deposit. The scope of works included gas wells equipment, construction of gas pressure reduction and metering point, pipelines, installation for gas drying , also other objects with auxiliary appliances. After installation commissioning, the mine was handed over for operation to the final client.
Information
Project name | Development of natural gas deposit, Kupno |
---|---|
Type of project | Realizacja Ropa i Gaz |
Client | PGNiG w Warszawie S.A. |
Duration | 2008 - 2009 |
Technical data | Pojemność czynna magazynu: 250 mln m3 Max wydajność zatłaczania 2,40 mld m3/dobę Max wydajność odbioru 9,60 mln m3/dobę |