The subject of the contract was the “Modernisation of the Wygoda power substation”, which included:

Task No. 1: Development of design documentation and performance of works related to the modernization of the Wygoda power substation, and Task No. 2: Development of design documentation and performance of works related to the connection of the Bochnia Traction Substation to the grid, involving:

  1. a) development of detailed and as-built designs for each task separately,
  2. b) development of a construction design together with obtaining building permits for each task separately,
  3. c) performance of construction and assembly works according to the developed design documentation in respect of task no. 1,
  4. d) performance of construction and assembly works according to the developed design documentation in respect of task no. 2,
  5. e) dismantling, liquidation of existing Wygoda power substation equipment, management of all waste generated during the implementation of the project,
  6. f) performance of tests and measurements necessary for the commissioning of the modernized power infrastructure in accordance with regulations.