Newsroom

Control Process will modernize the electricity station for Tauron

2014-08-28
Control Process will modernize the electricity station for Tauron

Today was solemny signed an agreement for task: „Modernization of GPZ Wygoda station between Tauron Distribution SA and Control Process Company.

Subject of an order is „Modernization of GPZ Wygoda station which includes:

Task number 1: preparation of design documentaction along with implementation of works related to the modernization of the station GPZ Wygoda and Task nuber 2: Preparation of design documentation, along with implementation of the work, associated with the connection of Traction Substation Bochnia in the following areas:
a) preparation of detailed design and as-built design for each task separately,
b) preparation of building permit design including obtaining building permits for reach task separately
c) implementation of erection and construction works according to the developed design documentation in terms of task number 1
d) implementation of erection and construction works according to the developed design documentation in terms of task number 2 
e) dismantling, decommissioning existing equipment of GPZ station Wygoda, making managment of all waste generated in the implementation of the subject of the agreement 
f) performance tests and measurements necessary to comply with the regulations undertaking into service modernized electricity infrastructure