Construction of the surface part of the underground gas storage Kosakowo
The subject of the project includes General Contracting of the surface part of the underground gas storage “Kosakowo” The surface infrastructure of the storage with the capacity 250 mln m3 includes: gas measuring unit , gas compressor station, gas drying installation, technological boiler unit with all buildings and auxiliary installations.
Information
Project name | Construction of the surface part of the underground gas storage Kosakowo |
---|---|
Type of project | Oil & Gas project |
Client | PGNiG S.A. |
Duration | 2011-2013 |
Technical data | Active capacity of the storage: 250 mln m3 Max capacity of injection 2,40 mld m3/day Max wydajność odbioru 9,60 mln m3/dobę |